Cooke School and Institute Project Progress – November 2019

Nov 26, 2019

  • Ongoing work at elevation from 2nd floor exterior roof area, beauty caps have been installed in the east facade curtain wall.
  • Stucco wall installation at roof top exterior wall is ongoing.
  • Ducts and pipes are being painted at gymnasium ceiling.